In WBS Gantt-Chart:
Holidays are taken into consideration when project start and finish dates are set. All holidays are managed in WBS Gantt-Chart's holiday calendar.
This is an example of the holiday calendar, showing two scenarios, A and B, as follows:
Scenario A
Yes / No | |
---|---|
Irregular holidays | Yes |
1st regular holiday | - |
2nd regular holiday | - |
Holidays | No |
Scenario B
Yes / No | |
---|---|
Irregular holidays | No |
1st regular holiday | Saturday |
2nd regular holiday | Sunday |
Holidays |
|
Note: is Monday.
Issue values
Value | |
---|---|
Start date |
|
Finish date |
|
Duration | 2 days |
Operations
Drag-and-drop the Gantt bar so the issue starts on .
Scenario A
This scenario does not have holidays, so the issue values are as follows:
Value | |
---|---|
Start date |
|
Finish date |
|
Duration | 2 days |
Scenario B
In this scenario, , , and will not be counted since they are defined as holidays.
Value | |
---|---|
Start date |
|
Finish date |
|
Duration | 2 days |
Click Calendars on the left-hand side of the Gantt configuration screen.
You do not set any specific days of the week as holidays.
The first regular holiday you specify. If you select Yes for irregular holidays, this would not be shown.
The second regular holiday you specify. If you select Yes for irregular holidays, this would not be shown.
This is a list of the dates you have registered as holidays.